New record in Karviná

Czechia has a new record-holder for largest battery energy storage system: a facility in the Karviná region with roughly 90 MW of capacity. According to the Energy Regulatory Office (ERÚ) licence database, with licences granted as of 12 November 2026, 46 battery storage facilities hold valid operating licences with a combined capacity of nearly 300 MW, and a further 31 storage projects are awaiting licences.

The top-ranked project is Podolupark Solar I, backed by Czech companies Second Foundation, RSJ Investments and Ungelt Group. Main investor Second Foundation cites 87 MW installed capacity and 180 MWh of storage capacity, while ERÚ's database lists about 5 MW more, at 92 MW. The facility is notable for being built on a former black-coal mining site near Stonava in the Karviná region.

Tušimice will soon surpass it

The same investor consortium is building BESS Tušimice in the Sokolov region with 200 MW of output and 400 MWh of capacity. It is already in an advanced construction phase and will soon surpass the Stonava record. Battery systems are supplied by Czech firm GAZ Energy, which developed its own control system for these projects. All these projects were built without state subsidies.

BESS Lipnice, located near Vintířov in the Sokolov region, is awaiting its licence. The second-largest storage facility, with 57 MW installed output and 120 MWh capacity, was built by a consortium of energy group SUAS GROUP and Slovak firm EIF.

Top-10 and incumbent utilities

ERÚ's top-10 licensed battery storage list includes Stonava/Podolupark Solar I at 92 MW; Vraňany/BESS Vraňany at 20.5 MW; Příbor/MOE CZ at 15.5 MW; Břeclav/MND BESS at 15.2 MW; Ostrava/Entasi at 13.2 MW; Vlkoš/Top Centrum at 12.9 MW; Velká Bíteš/Compensation Power Technology at 12.5 MW; Ostrava/ČEZ Energo at 10.3 MW; Stonava/Podolupark Solar II at 10.2 MW; and Královské Poříčí/SUAS BESS at 10 MW.

Separately, Sev.en, the group of financier Pavel Tykač, is completing large batteries at the Kladno and Chvaletice power plant sites totalling 160 MW of output and 320 MWh of capacity. The company plans to operate them partly in frequency containment/ancillary services and partly on the spot market, stabilising both physical and commercial fluctuations in the grid, according to Sev.en transformation project manager Pavel Farkač.

Czechia's BESS fleet is being built largely without subsidies, led by former coal sites and industrial investors rather than only incumbent utilities.