Provisional agreement on the European grids package

MEPs and the Irish Presidency of the Council reached a provisional agreement on Wednesday morning on revised EU rules designed to speed up permit-granting for renewable energy projects, electricity grids, storage facilities and recharging stations. The deal sits inside the broader European grids package and marks the first time EU law would impose binding maximum authorisation periods specifically on energy storage.

Deadlines ranging from three months to two years

Under the provisional text, approval deadlines must not exceed three months for solar energy equipment and co-located energy storage (excluding hydrogen), six months for stand-alone energy storage and recharging stations, and two years for pumped hydropower storage.

Three months for solar with co-located storage. Six months for stand-alone storage and recharging stations. Two years for pumped hydropower storage.

Grid connection procedures would be subject to a general three-month deadline, extendable to six months where duly justified, with a derogation for isolated or small connected systems such as those in the EU's outermost regions.

A single digital portal for all permitting steps

The agreement introduces a single national digital portal covering every stage of the permitting process, reducing the need for developers to file separately with multiple authorities. It also creates a dedicated EU-wide permitting framework for electricity grid infrastructure, recognising that grid build-out is now the binding constraint on connecting new storage capacity in several member states.

For storage developers, the deadlines are significant because authorisation has historically been one of the least predictable parts of project delivery. According to the European Parliament's own figures, storage installations can take between one and seven years to permit depending on the member state and technology, while transmission grids take around ten years, with permitting accounting for more than half of that time.

Origin and next steps

The reform stems from a European Commission proposal published on 10 December 2025 as part of the European grids package, which sits under the Competitiveness Compass and the Clean Industrial Deal. The Parliament–Council agreement is provisional: the text must first be approved by the European Parliament's Committee on Industry, Research and Energy (ITRE) and then by the full Parliament before it enters definitively into force.

If adopted in its current form, the regulation would replace a patchwork of national timelines with a common EU ceiling for storage authorisations — a change that market participants have long argued is needed to convert Europe's large announced battery pipeline into shovels in the ground.

Source: European Parliament press release