The European Union has moved a step closer to dismantling one of the biggest structural barriers to energy storage deployment. On 18 November 2026, negotiators from the Council presidency and the European Parliament reached a provisional political agreement on a directive to accelerate permit-granting procedures, filed as procedure 2025/0400(COD).
What the agreement covers
The directive is the permitting half of the European Grids Package, which the European Commission published in December 2025. The Commission tabled the permitting proposal, COM(2025) 1007, on 10 December 2025. The wider package also contains a revised Trans-European Networks for Energy (TEN-E) regulation, guidance on efficient grid connections and contracts for difference, and eight cross-border "Energy Highways" projects. The TEN-E revision is a separate file and is not covered by this agreement.
According to the Parliament's legislative observatory, the agreed text amends three existing laws: the Renewable Energy Directive (2018/2001), the Electricity Market Directive (2019/944) and the 2024 gas and hydrogen market directive (2024/1788). The Commission welcomed the deal in Brussels.
Fixed deadlines across 27 member states
The core of the agreement is a set of maximum permitting periods that would apply uniformly across the EU-27, replacing a patchwork of national timelines that in some member states stretched into years.
Solar PV with co-located storage would face a three-month ceiling, standalone battery energy storage systems and EV charging stations six months, and pumped-hydro storage two years.
Grid connection approvals would generally be capped at three months, extendable to six where justified reasons exist. The threshold below which small-scale solar, storage and charging installations are exempt from permitting would rise from 100 kW to 200 kW.
Digital portal and tacit approval
The provisional text introduces a single national digital portal for permit applications and allows member states to adopt a tacit approval mechanism, under which a project is deemed authorised if authorities fail to respond within the deadline. Renewable energy and grid projects would also be presumed to be of overriding public interest, a status member states could set aside only in duly justified cases involving cultural heritage or security and defence.
Next steps
The agreement is not yet law. It still requires a vote in Parliament's industry committee, approval by the full Parliament and the Council, and publication in the Official Journal. Only then would member states begin an 18-month transposition period. Experts cited by Global Energy News expect the rules to unlock a large pipeline of BESS and high-voltage transmission projects once implemented.
Source: Global Energy News (g-enews.com); Credence Research