A breakthrough for storage permitting timelines

Negotiators from the European Parliament and the Council have reached a provisional agreement on a proposal designed to accelerate permitting for renewable energy, electricity grids, energy storage installations and charging stations across the EU. For the storage sector, the deal introduces the first EU-wide maximum deadlines for authorisation procedures.

The deadlines in detail

Under the agreed text, permitting must be completed within:

  • Three months for solar equipment and associated energy storage systems, excluding hydrogen storage;
  • Six months for standalone energy storage systems and charging stations;
  • Two years for pumped hydro storage.

Grid connection deadlines are set at three months, extendable to six months where duly justified, with a derogation available for isolated or small connected grids such as those in the EU's outermost regions.

Smaller projects escape full authorisation

MEPs secured a rise in the capacity threshold at which authorisation is required for small solar installations, energy storage systems and charging stations, from 100 kW to 200 kW. In addition, no administrative permit will be needed for charging stations with a total capacity of up to 1 MW when installed on artificial structures.

For developers of sub-200 kW storage assets, the agreement effectively removes the administrative authorisation step altogether.

Community revenue sharing kicks in earlier

The threshold for mandatory revenue sharing with local communities was lowered from 10 MW to 7 MW. Projects developed by renewable energy communities are exempt, and member states retain the option to support vulnerable consumers and people affected by energy poverty through the resulting revenues.

The agreement also establishes that renewable energy and electricity grid projects will be considered to be in the overriding public interest, with member states able to derogate only in duly justified cases involving cultural heritage or security and defence. A single national digital portal will cover all permitting procedures, alongside a specific EU framework for permitting electricity grid infrastructure.

Next steps

The agreed text must now be submitted to the ITRE committee for a vote, and then approved by Parliament and the Council before publication in the Official Journal of the EU. Only then will the deadlines become binding on national permitting authorities.

Source: European Parliament