A pipeline moving from announcement to construction

Six developers have advanced large-scale battery energy storage projects in Germany totalling more than 4GWh toward construction. The activity is concentrated against a hard regulatory deadline: projects must reach final investment decision (FID) by 31 December 2026 and come online by 4 August 2029 to be eligible for the grid fee exemption. FID in this context means binding orders covering 50% of the total investment volume.

Elements Green signs with TenneT

Elements Green has signed a grid connection agreement with TenneT Germany for its 400MW/1,600MWh BESS in Stadorf, Lower Saxony. The agreement likely includes a flexible connection agreement (FCA). The developer will now undertake detailed planning of grid connection infrastructure and construction preparations.

Voltwise breaks ground in North Rhine-Westphalia

Voltwise Power has broken ground on its first German BESS, a 56MW/125MWh system in Leopoldshöhe, North Rhine-Westphalia, with commissioning planned for 2027. The project will use Fluence Smartstack AC block technology, with Santander arranging financing and Vattenfall providing route-to-market offtake.

EnBW takes FID at Forbach

EnBW has taken FID on a 41MW/170MWh BESS at its Forbach gas power plant. The battery will complement a new pumped storage plant EnBW is constructing at the same site. The utility already operates 20 small BESS projects totalling just over 100MWh and is building an 800MWh project at Philippsburg.

Flower files for 2GWh at Ragow

Flower has submitted building permit applications for a 500MW/2,000MWh BESS in Germany called Ragow, which it acquired last year. Flower expects ready-to-build status in 2027 and commercial operation in 2029. Developer DCES will oversee development, while Flower handles finance, EPC, operation and commercialisation.

Dispatch opens a retail bond

Dispatch has opened a retail bond offer of up to €2 million for its 3GW German BESS plans, called 'Germany T2'. The bonds have a three-year term, pay an 8% return and carry a minimum ticket size of €250. Over half the amount has already been raised. Dispatch previously deployed a 45MW/90MWh project in the Netherlands.

All BESS in Germany must contend with flexible connection agreements, under which system operators provide limited or restricted grid access in order to connect.

Green Flexibility's Lower Saxony programme, covered separately, adds a further 480MWh platform to the German construction pipeline.