Three large German projects reach new milestones
Germany's utility-scale battery storage pipeline moved forward on several fronts this week, with developers filing permits, signing grid agreements and taking final investment decisions across the country.
Ragow: 500 MW / 2 GWh in Brandenburg
Flower has partnered with German developer dces to build the Ragow project, a 500 MW/2,000 MWh four-hour battery energy storage system in Brandenburg, near Berlin. Flower acquired the project in 2025 and building permit applications have now been submitted. The target is ready-to-build status in 2027 and commercial operation in 2029. Under the split of responsibilities, dces will lead project development with Flower's support, while Flower handles financing, EPC, operation and commercialisation. dces reports a battery storage pipeline of 3 GW in Germany.
Stadorf: 400 MW / 1.6 GWh connected to TenneT's extra-high-voltage grid
Elements Green has finalised a grid connection agreement with TenneT Germany for a 400 MW battery system with 1.6 GWh of capacity and four-hour duration in Stadorf, Lower Saxony. The BESS will connect directly to the extra-high-voltage grid, making it one of the largest battery storage projects planned in Germany. The agreement follows a connection construction agreement signed in October 2026, which provides the contractual framework for construction and operation.
Forbach: EnBW takes FID on 46 MW / 170 MWh
EnBW has taken a final investment decision on a 46 MW/170 MWh four-hour battery at its Forbach power station in Baden-Württemberg. Construction is scheduled to begin in 2028, with commercial operation planned for 2029, complementing a new pumped-storage hydropower plant at the same site.
EnBW operates 20 battery storage systems in Germany with more than 100 MWh combined, and has a further 3,000 MWh of projects under development.
The Forbach BESS could qualify for Germany's grid fee exemption for large-scale battery storage if it enters operation by early August 2029. EnBW plans to expand an existing terraced area and reuse infrastructure from the former Murgwerk facility, including cable routes, the transformer area and the switchgear building. At its former nuclear site in Philippsburg, the company is building a 400 MW, roughly 1,000 MWh system it describes as one of the largest in Germany.
Policy backdrop
The momentum comes as German executives, policymakers and researchers discuss faster deployment of grid-scale storage to balance fluctuating wind and solar output and relieve grid bottlenecks. Germany's Federal Ministry for Economic Affairs and Climate Action has approved €500 million in funding for large-scale energy storage technologies, framed as critical to stabilising renewable-heavy power systems. On the transaction side, Flower Infrastructure Technologies also announced the divestment of a 63 MW battery storage project in Germany.
Source: Modern Power Systems; ess-news; Power Technology; Berlin Today