Gas wins first auction

Germany's Bundesnetzagentur awarded all 5.16 GW in the country's inaugural long-term capacity auction to gas-fired power plant projects, under 15-year contracts starting in 2031. The auction is the first phase under the Electricity Supply Security and Capacity Act (StromVKG).

RWE and LEAG won 99% of the awarded capacity with ten winning bids combined; the remaining bid went to a municipal authority. RWE secured support for seven projects and 58% of awarded capacity, while LEAG received state aid for three projects, reportedly involving conversion of lignite-fired plants to gas. The weighted average support was EUR 155,296 per MW per year versus a ceiling of EUR 244,000 per MW.

BESS bids effectively ineligible

Battery storage projects bid but were effectively ineligible. Rules required discharging at full power for ten hours continuously, recharging in three hours, then delivering at maximum capacity for eight hours. Few facilities currently exceed four hours of duration. A resilience rule also required essential components to be manufactured in the European Economic Area, and China dominates the battery technology market; gas plants faced no such requirement. Seven submitted projects were disqualified over the rules.

The first auction was designed around long-duration security of supply, a shape that today's lithium-ion BESS fleet cannot meet at scale.

Second auction and later phases

BNetzA has opened a call for the remaining 3.84 GW of the planned 9 GW, with a deadline of December 29. There were 41 bids totalling almost 12 GW in the first round. The next phase, generation capacity auctions, is expected to be more favourable to BESS, with conditions adjusted for short-duration flexibility, while demand response and existing facilities are to participate later.

Winning gas plants must operate fully climate-neutral from 2045, implying conversion to hydrogen, biomethane or biogas. That long-term requirement keeps a hydrogen link in the capacity mechanism, even if the first auction has delayed battery storage participation.

Source: Balkan Green Energy News