Two years after regulators approved Germany’s hydrogen core network, the grid is expanding slowly, according to gas grid operator association FNB Gas. Of the planned 9,040 km to be built by the 2030s, 537 km are currently in operation, with an additional 900 km planned by the end of 2027. Most operating pipelines are retrofitted existing natural gas pipelines; more than 500 km were already implemented last year.
First electrolysis-to-offtake chain in operation
FNB Gas highlighted a key recent milestone: electrolysis, transport and offtake are now operational. In Lingen, an RWE electrolysis plant produces renewable hydrogen that is transported via around 120 km of pipelines to the chemical park in Marl. The link demonstrates that the network is not only a pipe concept but is beginning to connect production with industrial demand.
FNB Gas also said Germany’s first commercial hydrogen cavern storage facility is due to come into operation in Epe in 2027. That would add storage capacity to a system that will need flexibility as hydrogen production and consumption scale.
Investment needs and demand risk
The Federal Network Agency (BNetzA) has said total investment for the hydrogen grid is expected to be around 19 billion euros. But the pace of network expansion is colliding with uncertainty over demand. Think tank IEEFA warned that demand projections have been overly optimistic, as electrification and cheaper energy sources are likely to limit hydrogen demand. That would create a lack of revenue for operators from transport fees, potentially leaving taxpayers with billions of euros of costs under a state-backed credit scheme used to finance the core grid.
FNB Gas called for reliable financing conditions, including continuation and expansion of the government support programme for industrial decarbonisation through Carbon Contracts for Difference (CCfDs), which also support hydrogen projects. The government announced the preparatory phase for the third round of the programme earlier this week.
Strategy goals under scrutiny
High production costs, weak demand and infrastructure uncertainty continue to hold back Germany’s hydrogen sector despite government pledges to ramp up the hydrogen economy. The government has faced criticism over funding cuts, and the Federal Court of Auditors said in a 2025 special report that Germany has not achieved its hydrogen strategy goals and is unlikely to do so in the near future.
The core network is therefore advancing, but not at the pace implied by the 9,040 km plan. The Lingen-Marl chain and the Epe storage project show concrete progress. The larger question is whether industrial demand, financing and policy support will arrive fast enough to justify the €19 billion grid investment.
Source: Hydrogen Central
This article was assisted by AI analysis. Please refer to the original source for official information.