Germany’s Bundesnetzagentur has published the terms for the country’s second long-term capacity auction of 2026, offering 3,840 MW of reduced capacity (rMW). Bids are due 29 December 2026, and bidders must complete authentication by 22 December 2026. The regulator will accept bids only electronically through its closed user group platform.

Ceiling and commitment period unchanged

The auction ceiling remains at 244,000 EUR per MW of reduced capacity per year, unchanged from the first round. Awards carry a 15-year commitment period. Battery storage can bid in pools for the 15-year commitment, making the auction relevant to German BESS developers looking for long-term revenue visibility.

First round cleared well below ceiling

The first 2026 round, with a bid date of 8 September, called 4,500 rMW and awarded around 5,160 rMW across 11 bids because the bid that first crossed the volume line was still awarded. The volume-weighted average price was 155,296 EUR per rMW per year, well inside the 244,000 EUR ceiling. Combined, the two 2026 rounds total around 9,000 rMW.

That first-round result gives the market a published benchmark. Battery projects that did not clear in September, or were not ready to bid, have a second entry point before year-end with the same ceiling and commitment length.

Pool rules and security requirements

Pool bids are allowed only if every unit in the pool belongs to the same technology class. A pool’s reduction factor is the average of its units’ factors weighted by nominal capacity. For battery storage, units in one pool may carry different reduction factors due to differing maximum discharge duration, which the regulator explicitly allows. Controllable loads and small-unit pools are not eligible for the long-term auctions.

Each bid requires a bid security of 15% of the ceiling multiplied by the reduced capacity bid, equal to 36,600 EUR per rMW, plus a fee of 956 EUR per bid. Security is sized on the ceiling rather than the bid value, so a 50 rMW pool posts 1.83 million EUR before the bid date. Successful bidders must post a completion security with the responsible transmission system operator by the 20th working day after award, equal to the non-completion penalty of 1.5 times the bid value multiplied by the reduced capacity.

A 15-year capacity payment is one revenue line among several. For German BESS assets, the business case still depends on stacking with balancing, ancillary services, tolling or a PPA. The second auction therefore matters, but it is not a standalone investment case.

Source: Synertics