First site under construction

Green Flexibility has started construction at Bad Bederkesa in Geestland, Lower Saxony, the first of six planned battery storage projects in the German state. The first plant is rated 10MW with 25MWh according to the developer, or 24MWh according to the Lower Saxony environment ministry, implying roughly 2.5 hours of duration at full power. Targeted start of operation is the second quarter of 2027.

A €150 million state-level platform

The wider Lower Saxony programme covers six sites intended to deliver about 120MW/480MWh — a four-hour average power-to-energy ratio — backed by approximately €150 million (US$165 million) of investment. Developer figures place the portfolio at 125MW/480MWh. The other planned sites are Lindern, Hagen im Bremischen, Esterwegen, Bremervörde and Zeven.

The other five sites are not confirmed as under construction, and there is no common completion date: commissioning dates differ by location.

Flexible connections under REGIOlink

Distribution network operator EWE NETZ has agreed flexible connection arrangements covering all six Lower Saxony projects, using Green Flexibility's REGIOlink concept to account for regional network conditions in managing import and export.

Flexible agreements can impose operating limits during network constraints. Precise contractual thresholds and curtailment requirements per site have not been published and are not a guarantee of unconstrained dispatch.

This matters for revenue modelling. A battery's ability to charge during negative-price periods and discharge during peaks is the core of most merchant cases in Germany, and a flexible connection can truncate exactly those windows when the local network is stressed.

Bavaria project outside the portfolio

Green Flexibility is separately developing a 40MW/90MWh battery installation at Obergünzburg in Bavaria, outside the six-site Lower Saxony portfolio, holding an open day in November ahead of a planned December construction start.

Why Lower Saxony

Germany's growing battery pipeline is partly a response to a system supplied by increasing wind and solar generation: storage absorbs surplus power and returns it later, and qualified installations can provide balancing services. Lower Saxony's concentration of wind generation makes it a logical location, but the grid-relief value of a battery depends on its connection location and charge/discharge control, not only on aggregate MWh figures.