LEAG Clean Power is building the GigaBattery Jänschwalde 1000, a 1 GW/4 GWh battery energy storage system in Jänschwalde, Brandenburg, about 15 km from the Polish border. The project is one of Germany's largest BESS developments and is designed to connect to the grid in 2028 — the same year the adjacent Jänschwalde coal-fired power plant is due to close.
Fluence supplies the technology. The system will use Fluence's Smartstack battery platform, built around the Smart Skid, a roughly 10-ton control and monitoring platform that acts as the system's brain. Battery modules are placed onto the skid; a 10 MWh module weighs about 20 tons. Smartstack is available in 7.5 MWh and 10 MWh versions, the latter since June 2026, and Fluence claims about 30% higher energy density than other market solutions. The platform can be configured for 2-, 4-, 6- or 8-hour durations; Jänschwalde is a 4-hour system.
A coal site becomes a clean-energy hub
The BESS occupies about 10 hectares within the still-operating Jänschwalde lignite power plant area. It is part of LEAG's wider GigawattFactory initiative, which combines wind farms, PV plants and storage. In September 2026, the roughly 105 MW Forst-Briesnig 2 wind farm was commissioned with 17 Vestas V162-6.2 MW turbines, along with the first roughly 130 MW phase of the Bohrau PV farm, using about 230,000 modules on about 130 hectares.
Both are about 5 km south of the storage site but will not share a grid connection point. The BESS will have its own grid connection on the power plant site.
Germany's giant BESS race
Jänschwalde will not hold the European capacity crown for long. Another German project, Klostermansfeld in Saxony-Anhalt, is being built by BW ESS with the same 1 GW power rating but a larger 5.7 GWh capacity. Both giant storage projects are scheduled to come online in 2028.
The scale reflects a new phase in the German market: batteries are moving from small grid-support units to infrastructure-sized assets at former conventional power sites. The Jänschwalde project pairs the closure of lignite generation with new wind, solar and storage, but the BESS will operate as a separate grid asset rather than sharing an interconnection with the nearby renewables.
Source: Gram w Zielone