Portugal has launched two competitive procedures offering a combined 1,050 MVA of grid connection capacity for battery storage, in one of the more direct national allocation mechanisms for storage seen in the European Union to date.
How the capacity is split
The larger of the two procedures reserves 750 MVA of grid connection capacity for standalone battery energy storage systems (BESS) — projects that charge from and discharge to the network without a dedicated co-located generation asset. The second offers 300 MVA for renewable generation projects that include co-located storage.
Applications are open until 22 December 2026.
The mechanism is a national storage capacity allocation: rather than simply granting grid access on a first-come, first-served basis, Portugal is competitively awarding scarce connection capacity to storage projects.
Why allocation mechanisms matter
Grid connection has become the binding constraint on storage deployment across much of the EU. A JRC assessment published this month identified grid connection delays, regulatory uncertainty and limited long-term revenue visibility as the persistent barriers holding back the bloc's storage build-out, with current capacity at 76 GW against the 172 GW projected as necessary by 2030.
Competitive allocation of connection capacity addresses the first of those barriers directly. It also gives regulators a tool to prioritise projects by maturity, size and system value rather than by queue position — an approach that has been discussed in several member states but implemented in only a handful.
Standalone storage takes the majority
The 75/25 split in favour of standalone BESS is notable. It signals that Portugal sees merchant or contract-backed storage as a standalone grid asset, not merely as an accessory to renewable generation. Standalone systems can capture arbitrage value across the full price curve and provide ancillary and balancing services, but they depend heavily on market design that allows revenue stacking.
The 300 MVA reserved for co-located storage, meanwhile, supports hybrid projects that can share interconnection infrastructure and improve the utilisation of existing grid capacity — a model that has proliferated in southern Europe as solar build-out has accelerated.
What comes next
The tender outcome will depend on how many developers can demonstrate project maturity by late December, and on whether Portugal's market arrangements offer sufficient revenue certainty to justify investment. With the application window closing on 22 December 2026, the awarded capacity should become visible early next year, providing one of the clearer signals yet of how a southern European member state intends to translate its 2030 storage ambitions into contracted megawatts.