Swedish battery storage company Flower has partnered with project developer dces group to develop the 500 MW/2 GWh Ragow battery energy storage project in Brandenburg, Germany, according to a Flower press release dated 16 November 2026.
A clean split of development and delivery
Under the agreement, dces group will oversee project development with support from Flower. Flower, which acquired the project in 2025, will be responsible for financing, engineering, procurement and construction, operation and commercialisation of the asset.
The structure separates the land, consenting and local stakeholder work — where specialist German developers typically hold the deepest expertise — from the capital-intensive delivery and trading functions that a pan-European storage operator can industrialise across a portfolio.
Permits filed, construction targeted for 2027
Building permit applications have already been submitted for the Ragow project. The scheme is expected to reach ready-to-build status in 2027, with commissioning targeted for 2029.
At 2 GWh, Ragow belongs to a small group of German projects that are sized like transmission assets rather than merchant batteries. The commercial model, not the technology, will determine whether it is replicated.
The scale places Ragow among the largest standalone battery projects announced in Germany to date, and it lands in a market where the pipeline of gigawatt-hour-class schemes has thickened considerably over the past 18 months. Brandenburg benefits from proximity to Berlin's load centre and to the high-voltage corridors that carry wind generation from the north-east toward southern demand.
Why the timeline matters
The 2029 commissioning target is significant for two reasons. First, it falls after 4 August 2029, the cut-off date set by Germany's Federal Network Agency for batteries to retain the grid fee exemption — a reminder that late-decade projects cannot underwrite their business case with that relief. Second, it means Ragow will be delivered into a market shaped by the EU's newly agreed permitting rules, which introduce binding time limits for standalone storage once transposed into national law.
For Flower, Ragow is a statement of intent in its largest continental market. For dces group, the partnership converts a development-stage asset into a de-risked construction pipeline without carrying merchant exposure.
The key open questions are the offtake structure — merchant trading, capacity payments or a hybrid route — and the grid connection agreement with the relevant Brandenburg network operator, neither of which has been disclosed in detail.